I have a problem when I try and run this job, This only started monday and I have been resetting and it will run but today it is not.
Please help
W_TABLE_STATS_00_JobControl..JobControl (@W_table_STATS_Hash): Controller problem: Error calling DSRunJob(W_table_STATS_Hash), code=-99
[General repository interface 'other error']
Regards
TP
Posted: Wed Aug 13, 2008 5:26 am
by ArndW
Welcome to DSXchange, TP.
Is this happening when calling the job from an execute job stage in a sequence job or from the Job Control section of a normal DataStage server job? What has changed in your system since Monday and are any other errors visible?
Posted: Wed Aug 13, 2008 6:10 am
by TP
Hello
Thanks
It is happening on a sequence and when I run it manually.
Nothing has changed at all. That is what confuses me.
ArndW wrote:Welcome to DSXchange, TP.
Is this happening when calling the job from an execute job stage in a sequence job or from the Job Control section of a normal DataStage server job? What has changed in your system since Monday and are any other errors visible?
Posted: Wed Aug 13, 2008 6:20 am
by ray.wurlod
If you reset the job in Director after it fails, do you get a "from previous run" event or a "phantom output" event in the job log?
If that doesn't work, try re-compiling the job.
Posted: Wed Aug 13, 2008 7:20 am
by chulett
Did you have any problems occur on Monday that you are aware of, particularly the partition where DataStage is installed running out of space for example?
Posted: Wed Aug 13, 2008 8:04 am
by TP
No there were no problems.
chulett wrote:Did you have any problems occur on Monday that you are aware of, particularly the partition where DataStage is installed running out of space for example? ...
Posted: Wed Aug 13, 2008 8:05 am
by TP
Yes I do get the "from previous run"
I have now compiled the job will run it and see what happens.
ray.wurlod wrote:If you reset the job in Director after it fails, do you get a "from previous run" event or a "phantom output" event in the job log?
If that doesn't work, try re-compiling the job. ...
Posted: Wed Aug 13, 2008 8:10 am
by TP
I ran the job and it is still giving the same error.
TP wrote:Yes I do get the "from previous run"
I have now compiled the job will run it and see what happens.
ray.wurlod wrote:If you reset the job in Director after it fails, do you get a "from previous run" event or a "phantom output" event in the job log?
If that doesn't work, try re-compiling the job. ...
Posted: Wed Aug 13, 2008 8:17 am
by chulett
TP wrote:Yes I do get the "from previous run"
You need to
post the contents.