hi,

i am migrating jobs from one server to another.
but when migrating i get the following error.

PROJECT IS NOT NLS COMPATIBLE.

the source project has no NLS settings. it is blurred as seen in administrator.but in target server the NLS button has many options when seen in administrator.

what can be he solution?
Vinay
ArndW
Participant
Posts: 16318
Joined: Tue Nov 16, 2004 9:08 am
Location: Germany
Contact:

Post by ArndW »

How are you migrating jobs? If you are doing a .dsx or .xml job export from the original to the new project and are importing them through the designer job import button then you should not be seeing any errors during the import process.

I know that there is an easier way, but I can't think of it or check now, but go to your $DSHOME directory and "cat uvconfig | grep NLSMODE" to see if it is set to "1".
ray.wurlod
Participant
Posts: 54607
Joined: Wed Oct 23, 2002 10:52 pm
Location: Sydney, Australia
Contact:

Post by ray.wurlod »

Code: Select all

$DSHOME/bin/analyze.shm -t0 | grep NLSMODE
IBM Software Services Group
Any contribution to this forum is my own opinion and does not necessarily reflect any position that IBM may hold.
vintipa
Participant
Posts: 136
Joined: Wed May 07, 2008 11:26 am
Location: Sydney, Australia
Contact:

Post by vintipa »

hi Good day :) ,

i am migrating the job categories using DS Version Control component.
there is no problem while migrating the jobs using DS Manager -> export and import options. but this problem arises when i use Version control.