How to run multiple jobs simultaneously in IA?

Post by amarnaath.ds »

Hi Team

When there are two jobs running in Information Analyzer, IA is not accepting any other job to run simultaneously, but put it in the queue, and then failed this job after 30 minutes. Here the job wait queue max time is 30 min.

Please help me to run IA jobs simultaneously. Is there any server setting that needs to be done to configure simultaneous runs?

Thanks in advance.
rjdickson
Participant
Posts: 378
Joined: Mon Jun 16, 2003 5:28 am
Location: Chicago, USA
Contact:

Post by rjdickson »

Are you running Workload Manager via the Operations Console in Information Server 9.1?
Regards,
Robert