I developed few Sequence Jobs in ADS 7.5 Version
I want to trasfer it to ADS 7.1 Version
is it possible without developement??

Thanks
Him

Posted: Mon Nov 07, 2005 9:20 pm
by vmcburney
That's tricky because sequence jobs changed a lot between those two versions. You could try exporting an empty 7.1 job and a full 7.5 job into text export files and then copy and paste stages from the full job to the empty job.

Posted: Mon Nov 07, 2005 9:54 pm
by kduke
You might be able to copy the job control code from a 7.5 sequence job to a 7.1 batch job. I doubt if you can import the job.

Posted: Mon Nov 07, 2005 11:26 pm
by kcbland
I suggest you use 2 PC's side-by-side and painstakingly recreate the job.

Posted: Tue Nov 08, 2005 5:00 am
by ray.wurlod
It may be possible. However, if you have use any of the activities that are new in 7.5 (StartLoop, EndLoop, UserVariables, Terminator), then it will not work.