Hi,

In our Project we want to implement Control Loading,Logic as follows.
1> Divide the total rows in the staging table by n(constant) adn obtain n ranges(group of rows).
2> Then Load each of range seperatley in the target table.
3> If any of the row in the ranges fails ,the entire range is rollbacked.
Note: The target load is direct load i.e there is no lookup performed.

e.g if total rows are 100 and n =10 ,then the ranges are 1..10,11..20 and so on

The Design that comes to my Mind is...



StagingTable-------------->Transformer--1 to n------------>TargetTable
Transformer- n+1 to 2n-------->TargetTable
Transformer- 2n+1 to 3n------->Target Table

Note: Target table is the same in all the range loading.

I want to know
1>wheteher this design is possible in DataStage
2> can we limit the number of rows that can be loaded in the Taget table
3> Can we start loading after rows after skipping specific number of rows
e.g fro n+1 to 2n range we have to skip first n rows and then start loading.

Thanks in advance,
Gokul Tendulkar



roy
Participant
Posts: 2598
Joined: Wed Jul 30, 2003 2:05 am
Location: Israel

Post by roy »

Hi,
If you precount the number of rows in your source data you can run a multipe instance or in a loop a job that passs P_MIN_VAL P_MAX_VAL then use them in the where part to each time read only 1 portion of the data.
you'll probably need to add somelogic around this, but that's the general idea.
IHTH,
Roy R.
Time is money but when you don't have money time is all you can afford.

Search before posting:)

Join the DataStagers team effort at:
http://www.worldcommunitygrid.org
Image
Gokul
Participant
Posts: 74
Joined: Wed Feb 23, 2005 10:58 pm
Location: Mumbai

Re: Control Loading of the Target table

Post by Gokul »

Thanks Roy,

Gokul wrote:Hi,

In our Project we want to implement Control Loading,Logic as follows.
1> Divide the total rows in the staging table by n(constant) adn obtain n ranges(group of rows).
2> Then Load each of range seperatley in the target table.
3> If any of the row in the ranges fails ,the entire range is rollbacked.
Note: The target load is direct load i.e there is no lookup performed.

e.g if total rows are 100 and n =10 ,then the ranges are 1..10,11..20 and so on

The Design that comes to my Mind is...



StagingTable-------------->Transformer--1 to n------------>TargetTable
Transformer- n+1 to 2n-------->TargetTable
Transformer- 2n+1 to 3n------->Target Table

Note: Target table is the same in all the range loading.

I want to know
1>wheteher this design is possible in DataStage
2> can we limit the number of rows that can be loaded in the Taget table
3> Can we start loading after rows after skipping specific number of rows
e.g fro n+1 to 2n range we have to skip first n rows and then start loading.

Thanks in advance,
Gokul Tendulkar